(Mt) – BADM 633 Cumberlands Week 9 Project Schedule Planning Reflection Paper

FIND A SOLUTION AT Academic Writers Bay

Unformatted Preview
Project Schedule Planning This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Project Schedule Planning • • • • • The Project Schedule Defining Activities Case study of WBS development Activity definition and Task dependencies Leads and lags . . . continued on next slide This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Project Schedule Planning (continued) • • • • • Milestones Activity Sequencing Gantt Chart Network Diagram Critical Path This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning The Project Schedule • A project schedule includes • the sequence of activities, • the duration planned for each activity, and • relationships or dependencies between the beginnings and ends of different activities. • The project schedule is created • AFTER the scope planning has created the WBS • BEFORE project resource planning This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Review: Scope Planning • WBS breaks down the deliverables into smaller units, ending with the work packages. • A work package is a clearly defined activity or group of activities whose duration can be estimated. This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Case Study: Wedding Deliverables This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Deliverables Decompose into Work Packages • • • • • • Shop for shoes Create guest list Tailoring and fitting Shop for dress Find caterer Cater the wedding • Print the invitations • Choose the bouquet • Wait for RSVPs • Mail the invitations • Finalize the menu This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Case Study: Wedding Deliverables This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Remember • WBS follows rule • There is no sequencing of tasks in the WBS This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Task Dependencies • Finish-to-start This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Task Dependencies • Start-to-start This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Task Dependencies • Finish-to-finish This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Types of predecessors • External predecessors • Outside the project, such as the previous party being out of the reception hall • Discretionary predecessors • Matter of preference: bridesmaids arrive before couple • Mandatory predecessors • Cannot do the following task until the predecessor is done: invitations must be addressed before they can be mailed This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Leads and Lags • Lag: One task must wait in relation to another task: This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Leads and Lags • Lead: The task must start before the predecessor is done: This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Milestones • A milestone is an important checkpoint—usually completion of a major task or a major set of tasks. • Target dates will be set later This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Milestones in Wedding Plan • • • • Invitations Sent Menu Finalized Location booked Bridesmaids’ dresses fitted This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Creating a Gantt Chart • Gantt Chart is a horizontal bar chart with a list of activities on the left and a timeline on the horizontal axis. • A traditional Gantt chart does not show dependencies; many current Gantt charts add the critical path and arrows to indicate tasks that precede other tasks. This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Gantt Chart for Wedding Plan This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Network Diagram • • • • Also known as PERT chart or PERT/CPM chart Illustrates task relationships Used to determine the critical path Software such as Microsoft Project can be used to create a network diagram. This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Network Diagram for Wedding This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Network Diagram: Activity on Arrow • Alternative method • More difficult to read and understand • May require the creation of dummy activities when a task has multiple predecessors and multiple dependent tasks • More “mathematical” in its illustration of activities and events. This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning The critical path • When multiple paths exist through the network diagram, the path with the longest duration is called the critical path • If any task on the critical path is delayed, the project is delayed • Tasks NOT on the critical path have slack available. This is the amount of time the task could be delayed without delaying the completion of the project This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Critical Path Exle This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Critical Path Exle In this exle the critical path is A,B,C,D,E,F,I,L, and the earliest completion date for the project is the sum of the estimated times for all the stages on the critical path – 28 weeks This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Slack • Slack is the amount of time a task could be delayed without delaying the completion of the project • Tasks on the critical path have zero slack • For tasks NOT on the critical path, work backwards from the project duration to determine the amount of slack This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Slack on Critical Path Exle In this exle the slack for task K is 2 weeks. If task K is delayed by less than two weeks, it will not delay the completion date of the project. This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Types of Slack • Total Slack • Allowable delay of an activity without delaying project completion (usual meaning of “Slack” if not specified) • Free Slack • Allowable delay of an activity without affecting the earliest start of any dependent (following) activity • Safety Slack • Remaining allowable delay of an activity if all predecessors finish as late as possible This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Network Diagram compared to Gantt • Network diagram is more technical, helps determine the critical path • Network diagram is not to a scaled timeline • Gantt is easy to read and explain to non-technical people • Gantt has a good method for graphically illustrating task progress and whether things are ahead of schedule or behind This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Network Diagram compared to Gantt • Project managers depend on network diagram to plan and to adjust • Gantt is developed from network diagram for purposes of communicating the plan • Both are easily produced from project management software This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Finalizing the Project Schedule • May have to negotiate with sponsor or adjust customer expectations • Schedule will be impacted by Project Resource plans • Monitor the critical path tasks most closely This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Project Schedule Planning Summary • The Project Schedule shows when each activity will take place and the dependencies between activities • Activities or work packages are derived from the WBS, which was developed in Project Scope Planning • Task dependencies may be • • • • Finish to start Start to start Finish to finish Leads and lags . . . continued on next slide This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Project Schedule Planning Summary (continued) • Milestones are checkpoints • Activity Sequencing is determined by the dependencies • Gantt Chart is a horizontal timeline showing when each activity is scheduled, along with optional indicators of task progress • Network Diagram helps Project Managers illustrate task dependencies and determine the critical path . . . continued on next slide This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Project Schedule Planning Summary (continued) • Tasks on the critical path have no slack • If a critical path task is delayed, project completion will be delayed • Tasks not on the critical path have slack. • If a non-critical task is delayed by less than the slack, project completion will not be delayed. . . . continued on next slide This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Project Schedule Planning Summary (continued) • After the schedule is developed: • Get approval from sponsor; may require some negotiations • Next step will be to develop the project resource plan • Project Resource Planning may cause schedule adjustments This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning Questions? This work is licensed under a Creative Commons Attribution 3.0 Unported License (CC-BY). Project Management Chapter 10: Project Schedule Planning

Order from Academic Writers Bay
Best Custom Essay Writing Services

QUALITY: ORIGINAL PAPER NO PLAGIARISM - CUSTOM PAPER

Why Choose Us?

  • non-plagiarized Papers
  • 24/7 /365 Service Available
  • Affordable Prices
  • Any Paper, Urgency, and Subject
  • Will complete your papers in 6 hours
  • On-time Delivery
  • Money-back and Privacy guarantees
  • Unlimited Amendments upon request
  • Satisfaction guarantee
SATISFACTION
SATISFACTION

How It Works

  • Click on the “Place Your Order” tab at the top menu or “Order Now” icon at the bottom and a new page will appear with an order form to be filled.
  • Fill in your paper’s requirements in the "PAPER DETAILS" section.
  • Fill in your paper’s academic level, deadline, and the required number of pages from the drop-down menus.
  • Click “CREATE ACCOUNT ; SIGN IN” to enter your registration details and get an account with us for record-keeping and then, click on “PROCEED TO CHECKOUT” at the bottom of the page.
  • From there, the payment sections will show, follow the guided payment process and your order will be available for our writing team to work on it.

About AcademicWritersBay.com

AcademicWritersBay.comnbsp;is an easy-to-use and reliable service that is ready to assist you with your papers 24/7/ 365days a year. 99% of our customers are happy with their papers. Our team is efficient and will always tackle your essay needs comprehensively assuring you of excellent results. Feel free to ask them anything concerning your essay demands or Order.

AcademicWritersBay.com is a private company that offers academic support and assistance to students at all levels. Our mission is to provide proficient andnbsp;high quality academic servicesnbsp;to our highly esteemed clients. AcademicWritersBay.com is equipped with competent andnbsp;proficient writersnbsp;to tackle all types of your academic needs, and provide you with excellent results. Most of our writers are holders ofnbsp;master's degreesnbsp;ornbsp;PhDs, which is an surety of excellent results to our clients. We provide assistance to students all over the world.
We provide high quality term papers, research papers, essays, proposals, theses and many others. Atnbsp;AcademicWritersBay.com, you can be sure ofnbsp;excellent gradesnbsp;in your assignments and final exams.

NO PLAGIARISM
NO PLAGIARISM
error: Content is protected !!